Solar panels for warehouses in Yeovil

The economics of a Yeovil rooftop array turn on how much of the generation the occupier uses on site. The survey measures the roof, not the postcode: cladding profile, purlin centres, remaining sheet life and the load the frame can take.

923 kWh per kWp a year at this latitude, so a 500 kWp array models at about 462,000 kWh. Source: EU PVGIS v5.2, SARAH3, 10 degree pitch, 14 percent system loss.

Book a roof survey in Yeovil
96 m phase 1
Drawing Yeovil unit
Roof 96 x 62 m
Array 500 kWp
Yield 462,000 kWh/yr
Scale 1:500 / Rev A / BA20

Illustrative layout for a unit of this size. Your own figures come from the roof survey.

Yeovil / Somerset
South West industrial estate on the edge of a market town, with rooftop solar
Industrial stock of the kind we survey across South West.

Warehouse rooftop solar across Somerset

What a roof in Yeovil actually generates

Modelled irradiation at this latitude is 1180 kWh per square metre a year in the plane of a shallow-pitched roof, which works out at 923 kWh for every kWp installed (EU PVGIS v5.2, SARAH3, 10 degree pitch, 14 percent system loss). That is around 4 percent above the mean across the towns we cover, which is as good as UK rooftop gets outside the south coast.

Distribution stock around Yeovil clusters on A30, A37 and A303, which is where the large single-let roofs are.

Most of the units we look at here sit in the BA postcode area.

Dorset is the planning authority for most sites here, and the built-up area holds a population of about 50,170, so the stock here runs to trade counters, light industrial terraces and the occasional larger shed (ONS Census 2021 built-up areas).

FIG. 1 What a Yeovil roof makes, month by month

What a Yeovil roof makes, month by month

Modelled output per kWp installed, for a shallow-pitched south-facing array. Source: EU PVGIS v5.2.

050100Jan: 26 kWh per kWpJanFeb: 41 kWh per kWpFebMar: 76 kWh per kWpMarApr: 108 kWh per kWpAprMay: 125 kWh per kWpMayJun: 126 kWh per kWpJunJul: 127 kWh per kWpJul127 kWh Aug: 108 kWh per kWpAugSep: 83 kWh per kWpSepOct: 50 kWh per kWpOctNov: 31 kWh per kWpNovDec: 22 kWh per kWpDec

Jul produces 5.8 times what Dec does on the same roof. A 500 kWp array here models at about 462,000 kWh across the year, but it arrives unevenly, which is why we size against your summer daytime load and then look at whether storage is worth adding for the shoulder months.

Monthly figures as a table
MonthkWh per kWp500 kWp array
Jan2613,000
Feb4120,500
Mar7638,000
Apr10854,000
May12562,500
Jun12663,000
Jul12763,500
Aug10854,000
Sep8341,500
Oct5025,000
Nov3115,500
Dec2211,000
Source: EU PVGIS v5.2
FIG. 2 Yeovil against the rest of Somerset
  • Weston-super-Mare934
  • Bridgwater931
  • Yeovil923
  • Glastonbury913
  • Taunton911
  • Bath904
  • Wells899
  • Frome894

Yeovil ranks 3 of 8 towns we cover in Somerset on modelled yield, against a national mean of 886 kWh per kWp. The county runs from 894 to 934, a spread of 40 kWh per kWp. Within Somerset that difference is small enough to ignore: where the building sits is not what decides this scheme, your consumption pattern is.

Bars are zero based, so length is proportional to the figure. Where a county is flat, that is the finding: location is not the lever, consumption is. Source: EU PVGIS v5.2, modelled per town

Solar already consented near BA20

From the government's Renewable Energy Planning Database, Q1 2026. These are the schemes on record in this postcode district, which is a fair guide to how the local network has been treating export applications.

Scheme Operator Capacity Mounting Status
Tesco Queensway Place Push Energy 0.3 MW Roof Operational
Westland Leisure Complex Engie 0.22 MW Roof Operational
Morrisons, Lysander Road - Solar Panels Gondola Pro 0.37 MW Roof Application Refused

Grid connection through National Grid Electricity Distribution

Connections around Yeovil are handled by National Grid Electricity Distribution, which sets the export limit for the site. Above 3.68 kW per phase the connection runs under G99, so the export limit is agreed in advance rather than assumed. Where the local network is constrained, an export-limited connection usually still makes the scheme work, because a warehouse uses most of what the roof makes during the working day.

Across Somerset the planning database records 223 solar schemes totalling 1574 MW, of which 79 are operational (REPD Q1 2026).

Book the survey

Send us the postcode

Tell us where the unit is and roughly how big the roof is. We come back with what it can carry, what it would generate against your consumption, and the three ways to pay for it.

Lenzie Consulting Ltd arranges the survey and passes your details to our MCS-certified installation partner so they can quote.

We pass your details to our MCS-certified installation partner so they can quote. Read the privacy notice.

Questions about solar in Yeovil

What would a 500 kWp array produce in Yeovil?
Yes, and the number matters more than the sunshine. At 923 kWh per kWp a year, a 500 kWp array on a Yeovil roof models at around 462,000 kWh. What changes the answer is how much of that you use on site rather than export. Source: EU PVGIS v5.2, SARAH3, 10 degree pitch, 14 percent system loss.
Which network operator handles the connection in Yeovil?
Applications go to National Grid Electricity Distribution, who run the network across Somerset. They decide the export limit, and we handle the G99 paperwork alongside the array design.
What does Dorset require for rooftop solar?
Roof-mounted panels on a commercial building usually fall under permitted development, subject to the limits on projection above the roof plane and to the building not being listed or in a conservation area. We confirm the position with Dorset before the design is finalised.
Has anyone near BA20 already done this?
The planning database records 3 solar schemes in this postcode district, 3 of them roof mounted. That matters less as proof that it works and more as evidence of how the local network has been treating export applications. Source: Renewable Energy Planning Database, Q1 2026.