Solar panels for warehouses in Brentwood

Most of the industrial stock around Brentwood carries a large, shallow-pitched roof that was never asked to do anything. Each survey records the cladding profile, the usable area once rooflights and plant are removed, and the export limit worth applying for.

913 kWh per kWp a year at this latitude, so a 500 kWp array models at about 457,000 kWh. Source: EU PVGIS v5.2, SARAH3, 10 degree pitch, 14 percent system loss.

Book a roof survey in Brentwood
96 m phase 1
Drawing Brentwood unit
Roof 96 x 62 m
Array 500 kWp
Yield 457,000 kWh/yr
Scale 1:500 / Rev A / CM14

Illustrative layout for a unit of this size. Your own figures come from the roof survey.

Brentwood / Essex
Distribution estate in the east of England with solar arrays on several roofs
Industrial stock of the kind we survey across East of England.

Distribution centre solar across Essex

What a roof in Brentwood actually generates

Modelled irradiation at this latitude is 1173 kWh per square metre a year in the plane of a shallow-pitched roof, which works out at 913 kWh for every kWp installed (EU PVGIS v5.2, SARAH3, 10 degree pitch, 14 percent system loss). That is around 3 percent above the mean across the towns we cover, which is as good as UK rooftop gets outside the south coast.

We survey across the CM postcode area, starting from CM14.

Brentwood is the planning authority for most sites here, and the built-up area holds a population of about 55,340, so the stock here runs to trade counters, light industrial terraces and the occasional larger shed (ONS Census 2021 built-up areas).

FIG. 1 What a Brentwood roof makes, month by month

What a Brentwood roof makes, month by month

Modelled output per kWp installed, for a shallow-pitched south-facing array. Source: EU PVGIS v5.2.

050100Jan: 25 kWh per kWpJanFeb: 39 kWh per kWpFebMar: 74 kWh per kWpMarApr: 106 kWh per kWpAprMay: 121 kWh per kWpMayJun: 126 kWh per kWpJunJul: 127 kWh per kWpJul127 kWh Aug: 107 kWh per kWpAugSep: 84 kWh per kWpSepOct: 52 kWh per kWpOctNov: 31 kWh per kWpNovDec: 22 kWh per kWpDec

Jul produces 5.8 times what Dec does on the same roof. A 500 kWp array here models at about 457,000 kWh across the year, but it arrives unevenly, which is why we size against your summer daytime load and then look at whether storage is worth adding for the shoulder months.

Monthly figures as a table
MonthkWh per kWp500 kWp array
Jan2512,500
Feb3919,500
Mar7437,000
Apr10653,000
May12160,500
Jun12663,000
Jul12763,500
Aug10753,500
Sep8442,000
Oct5226,000
Nov3115,500
Dec2211,000
Source: EU PVGIS v5.2
FIG. 2 Brentwood against the rest of Essex
  • Colchester953
  • Canvey Island945
  • Southend-on-Sea942
  • Basildon933
  • Braintree932
  • Chelmsford930
  • Grays927
  • Brentwood913
  • Harlow908

Brentwood ranks 9 of 10 towns we cover in Essex on modelled yield, against a national mean of 886 kWh per kWp. The county runs from 908 to 973, a spread of 65 kWh per kWp. On a 500 kWp array that is about 32,500 kWh a year between the strongest and weakest town in the county.

Bars are zero based, so length is proportional to the figure. Where a county is flat, that is the finding: location is not the lever, consumption is. Source: EU PVGIS v5.2, modelled per town

Grid connection through UK Power Networks

UK Power Networks is the network operator here, and their answer on export capacity shapes the design. Any commercial array above 3.68 kW per phase connects under G99 rather than G98, and the application fixes what you are allowed to push back onto the network. If the local network is tight, limiting export rarely breaks the case here: most of the generation is consumed on site while the building is working.

Across Essex the planning database records 221 solar schemes totalling 2787 MW, of which 46 are operational (REPD Q1 2026).

Book the survey

Send us the postcode

Tell us where the unit is and roughly how big the roof is. We come back with what it can carry, what it would generate against your consumption, and the three ways to pay for it.

Lenzie Consulting Ltd arranges the survey and passes your details to our MCS-certified installation partner so they can quote.

We pass your details to our MCS-certified installation partner so they can quote. Read the privacy notice.

Questions about solar in Brentwood

What would a 500 kWp array produce in Brentwood?
Yes, and the number matters more than the sunshine. At 913 kWh per kWp a year, a 500 kWp array on a Brentwood roof models at around 457,000 kWh. What changes the answer is how much of that you use on site rather than export. Source: EU PVGIS v5.2, SARAH3, 10 degree pitch, 14 percent system loss.
Which network operator handles the connection in Brentwood?
Applications go to UK Power Networks, who run the network across Essex. They decide the export limit, and we handle the G99 paperwork alongside the array design.
What does Brentwood require for rooftop solar?
Roof-mounted panels on a commercial building usually fall under permitted development, subject to the limits on projection above the roof plane and to the building not being listed or in a conservation area. We confirm the position with Brentwood before the design is finalised.